Client:
Harmony GoldLocation:
Welkom, Free State Province, South AfricaDuration:
2 Years and 6 MonthsScope of Work:
The project at Phakisa Mine involved shaft rehabilitation through a self-mined area between 140 m to 180 m in depth.
This is an old rectangular shaft with six compartments which makes it unique to conventional shafts in the industry. The shaft was sunk in the 1940's and changed to a ventilation shaft in 2003. A balloon and aerocrete expanding foam concrete were used for the project.

Balloon Structure
Used To Create A Safe Platform For Refurbishment

40m Refurbished Area Depth

Innovative Approach
To Complete The Project