Regresar

Cliente:

Newmont

Lugar:

Northern Territory, Australia

Duración:

60 Months (Commenced 2021)

Alcance del trabajo:

Excavación de piques y chimeneas
Desarrollo minero
Servicios especializados
Construcción subterránea

The Tanami Shaft Lining & Equipping Project,
located in the Tanami Desert, Northern
Territory, is a significant expansion project
for Newmont Australia. Redpath’s role
encompasses complex shaft lining and
equipping activities.

Redpath’s scope at Tanami includes the concrete lining and equipping of a new shaft,
installing steel guides, and constructing essential infrastructure such as the headframe,
winder house, and compressor house. An overland conveyor and permanent winder ropeup further enhance material handling efficiency. Redpath’s team is also responsible for
commissioning the hoisting system, ensuring a reliable setup for Newmont’s underground
operations. This project highlights Redpath’s expertise in complex shaft infrastructure.

HEADFRAME CONSTRUCTION

HOISTING SYSTEM
COMMISSIONING

SHAFT CONCRETE
LINING

 

Regresar