Cliente:

Rio Tinto Coal Australia Pty Ltd

Lugar:

Queensland, Australia

Duración:

2 años

Alcance del trabajo:

Construcción subterránea
Excavación Mecánica

The Kestrel Mine produces approx. 4 million tons of high-volatile coking and thermal coal annually for the export market, using the longwall mining method.

The Kestrel Mine Extension project (KME) included the development of two mine-access drifts and the associated in-seam coal development to allow the commencement of longwall mining activities. The first drift was 4.75 m high x 6.5 m wide and 1,425 m long at a grade of 1 in 6. The second drift is 4.5 m high x 6 m wide and 1,673 m long at a grade of 1 in 8.

The in-seam work included drivage to establish the primary ventilation circuit, the tailgate drive-head area and sufficient pit room for multiple development headings. This was followed by the development of the first longwall block.

Construction activities included roadheader excavation, steel-set installation, concrete invert, rock bolting, continuous miner excavation, shotcrete application, and permanent services installation.

Project Image - Kestrel Mine - Access Drift

4.75m High By 6.5m Wide

Access Drift 1,425m Long

Project Image - Kestrel Mine - Mechanical Excavation Drift Development

Mechanical Excavation Drift Development

Utilizing Onboard Bolters & Shotcrete Boom Attached To Roadheader

Project Image - Kestrel Mine - Access Drift 2

4.5m High By 6m Wide

Access Drift 1,673m Long